Re-Hose of Komatsu WA 900

Date: April 2014
Details of the job:

Hosepower was engaged by a large Northern Territory mining company to undertake a full re-hose of an entire WA 900 loader as part of a complete machine rebuild. Hosepower manufactured and installed:

  • All pilot lines
  • Oil cooler lines
  • High pressure lines – up to 2 inch, 6 wire hoses

Hosepower provided 2 trained and experienced staff for approximately 1 week to undertake the re-hose. Staff were fully inducted onto site and were required to participate in all daily OH&S briefings and SOPs. During commissioning of the machine, Hosepower were present to ensure nil defects.